Progress Report – Unfortunately due to bad weather and high winds the tower crane erection has been deferred to the half term break which has meant that the work has been delayed by two weeks.   Work has been busy on site over the weekend in order to reduce the time lost to the weather.

Perimeter scaffold and birdcage scaffolding has now been erected to allow roof access for the roof carcassing works which will commence in the next week.