Work is progressing well at Lambrook School – the power change works were completed smoothly, ply hoardings have now been erected along with the tower crane which has been connected to a generator on site.  The steel work is currently being built and is due to be completed by the end of the week and the ground worker is presently excavating and laying drain and duct runs.  Some of the sub structure masonry has now been built to allow make up levels in advance of the Ground Floor beam and block being delivered.